-
- Influencer
- Posts: 10
- Liked: never
- Joined: Feb 27, 2017 8:50 pm
- Contact:
[MERGED] Feature Request : Linked SureBackup Jobs
We have roughly 12 SureBackup jobs that we are running weekly. For the last few weeks we have been adjusting the time that each job starts in order to minimize the amount of time it takes for them all to complete.
I would like to request the ability to link 1 SureBackup job to another. This way we can have 1 scheduled to start in the morning and the other jobs will kick off immediately following the 1st jobs completion.
Thanks,
Paul
I would like to request the ability to link 1 SureBackup job to another. This way we can have 1 scheduled to start in the morning and the other jobs will kick off immediately following the 1st jobs completion.
Thanks,
Paul
-
- Veeam Software
- Posts: 21139
- Liked: 2141 times
- Joined: Jul 11, 2011 10:22 am
- Full Name: Alexander Fogelson
- Contact:
Re: Chain SureBackup Jobs
Hi Paul, thanks for the request. Please review this thread for some workarounds.
-
- Novice
- Posts: 7
- Liked: 1 time
- Joined: Aug 14, 2017 12:16 pm
- Contact:
[MERGED] SureBackup schedule after another SureBackupJob
It sometimes seems convenient to schedule SureBackup job after another SureBackup job, not after Backup job. There is only one lab, and you can't run SureBackup if the lab is busy with another SB-job. It's just good to have them run consequently, one-by-one.
Is this feature possible?
Or maybe some kind of option like "retry 3 times in 15 minutes if resource (lab) is busy" would be even much better.
Is this feature possible?
Or maybe some kind of option like "retry 3 times in 15 minutes if resource (lab) is busy" would be even much better.
-
- Product Manager
- Posts: 14726
- Liked: 1706 times
- Joined: Feb 04, 2013 2:07 pm
- Full Name: Dmitry Popov
- Location: Prague
- Contact:
Re: Chain SureBackup Jobs
Hello LazyLoneLion.
Thank you for your request! I've merged your post to existing discussion, take a look for the suggested workaround.
Thank you for your request! I've merged your post to existing discussion, take a look for the suggested workaround.
-
- Expert
- Posts: 124
- Liked: 22 times
- Joined: Jul 30, 2015 7:32 pm
- Contact:
Re: Chain SureBackup Jobs
Maybe one day Veeam will add this feature that has been needed for a long time, but until then, their recommendation is to use Powershell to chain the jobs. I used individual jobs to test the configuration and then rolled them into one giant SureBackup job that tested multiple backup job data at once. It takes more than 18 hours to test all of my VMs, so I have two virtual labs on two different hosts and now I can complete in 12-18 hours and have every VM tested.
-
- Veteran
- Posts: 259
- Liked: 40 times
- Joined: Aug 26, 2015 2:56 pm
- Full Name: Chris Gundry
- Contact:
[MERGED] SureBackup - Schedule job to run after another SureBackup job
Can someone confirm it's NOT possible to schedule a SureBackup job after another SureBackup job? We want to run 3 SB jobs back to back, but it doesn't seem to be possible...? Thanks
-
- Veteran
- Posts: 1943
- Liked: 247 times
- Joined: Dec 01, 2016 3:49 pm
- Full Name: Dmitry Grinev
- Location: St.Petersburg
- Contact:
Re: SureBackup - Schedule job to run after another SureBackup job
Hey Chris,
Yes, it's not possible to schedule from the UI, but there is a workaround described in this thread.
Please review this discussion above.
Thanks!
Yes, it's not possible to schedule from the UI, but there is a workaround described in this thread.
Please review this discussion above.
Thanks!
-
- Veteran
- Posts: 411
- Liked: 31 times
- Joined: Nov 21, 2014 10:05 pm
- Contact:
[MERGED] Feature request, run job after a surebackup job
Hi,
I'd need to run a job after surebackup finishes.
However, on the Schedule page there are only backup jobs available for selection in "After this job:" radial button.
I'd need to run a job after surebackup finishes.
However, on the Schedule page there are only backup jobs available for selection in "After this job:" radial button.
Bed?! Beds for sleepy people! Lets get a kebab and go to a disco!
MS MCSA, MCITP, MCTS, MCP
VMWare VCP5-DCV
Veeam VMCE
MS MCSA, MCITP, MCTS, MCP
VMWare VCP5-DCV
Veeam VMCE
-
- Product Manager
- Posts: 6551
- Liked: 765 times
- Joined: May 19, 2015 1:46 pm
- Contact:
Re: Feature request, run job after a surebackup job
Hi,
May I ask you to provide more details about the use case? For now I can only suggest to utilize PowerShell to create a script that will continuously monitor the surebackup job status and kick off the backup job when SB job finishes.
Thanks!
May I ask you to provide more details about the use case? For now I can only suggest to utilize PowerShell to create a script that will continuously monitor the surebackup job status and kick off the backup job when SB job finishes.
Thanks!
-
- Veteran
- Posts: 411
- Liked: 31 times
- Joined: Nov 21, 2014 10:05 pm
- Contact:
[MERGED] Feature request, run job after a surebackup job
I want to run another surebackup job after the first one finishes. Now I have to guestimate the end time for first surebackup job.
Bed?! Beds for sleepy people! Lets get a kebab and go to a disco!
MS MCSA, MCITP, MCTS, MCP
VMWare VCP5-DCV
Veeam VMCE
MS MCSA, MCITP, MCTS, MCP
VMWare VCP5-DCV
Veeam VMCE
-
- Product Manager
- Posts: 20413
- Liked: 2302 times
- Joined: Oct 26, 2012 3:28 pm
- Full Name: Vladimir Eremin
- Contact:
Re: Chain SureBackup Jobs
Kindly, check reply above, there are some workarounds available. Thanks!
-
- Expert
- Posts: 128
- Liked: 40 times
- Joined: Nov 02, 2019 6:19 pm
- Contact:
Re: Chain SureBackup Jobs
I see this was first requested back in 2013 so I suspect it isn't ever going to be implemented but put me down for a +1 anyway!
-
- Lurker
- Posts: 1
- Liked: never
- Joined: Feb 23, 2023 8:05 am
- Contact:
Re: Chain SureBackup Jobs
2023 still not implementet would just like to join the chrous of "why can't this be a UI feature?"
Who is online
Users browsing this forum: No registered users and 59 guests